Leading window restoration specialist, Associated Steel Window Service (ASWS), has begun work on a large-scale contract atop one of London’s best known retail establishments, where exposure to the elements will pose as many challenges as the form and condition of the structure itself.
In successfully tendering for the key package on the historic Barkers of Kensington project, ASWS is renewing its relationship with McLaren Construction; having recently renovated and replaced a wide range of fenestration types for the main contractor during the landmark conversion of the north-east quadrant building at Oxford Circus to create Ikea’s new flagship store.
Originally founded by John Barker in 1870 as a small draper’s business, the Kensington site was rebuilt in the Art Deco style using designs by Bernard George and reopened in 1933, though the advent of the Second World War meant the redevelopment was not fully completed until 1958. The central atrium with its fully glazed roof comprising nine-barrel vaults was created as part of a £120 million mid-80s reconfiguration led by Fitzroy Robinson and Partners.
The main driver for the latest intervention under the guidance of Emrys Architects is the very poor condition of the decades old solar film applied to the roof glazing. And, although there are walkways between the barrel vaults, the client will be erecting a special track-mounted gantry which will give access to the upper areas of glass.
The Operations Director for ASWS, Kris Bennell, commented: “We are pleased to be back working for McLaren, including with several members of the management team we know from our involvement on 214 Oxford Street. In total, there are some 2,000 panes of glass where the ageing solar control film is being removed, before new German-made Llumar film is applied and a warranty-compliant sealant applied around edges to the film. We are also now finding significant numbers of panes of glass which have broken which we will be replacing and renewing all of the silicone around the wing clamping profiles.”
During the first phase, due to complete in November, ASWS is carrying out the removal and replacement of the degraded film as well any damaged glass across the lower levels. Then, when the temporary gantry is ready, Phase 2 will take a further seven months, ending in Summer 2027.
Jack Wright, Project Manager, at McLaren Construction adds “Having built a great relationship with Kris, Laura and the team at 214 Oxford Street it was an easy decision to pick up the phone and ask them to tender on the package at Barkers. I’m looking forward to working with them again on another great project at Barkers of Kensington.”